The new stadium site continues to be a hive of activity with work to areas of the basement and ground floor progressing.
The latest developments can be seen in the official images above.
The dismantling of the North East corner is largely complete with the majority of the east and north stand corner sections removed. The focus in this part of the ground is switching to getting it clear and accessible ready for the new season with the installation of the temporary staircases underway.
The basement slab in some of the northern parts of the new stadium is complete with work on the ground floor slab to those areas being progressed.
Revision to Main West Entrance
The Club can confirm that it has received planning permission from Haringey Council for a revision to the main west stand High Road entrance of the new stadium.
The revision, which was submitted to Haringey Council last month, replaces the original escalator box design and sees the introduction of a sculptured glass arch which forms part of the main entrance.
We are delighted that the scheme continues to progress and shall keep fans updated. Current works on site can be viewed via the Stadium TV section…